Highland Meadows First and Second Additions - District No. 1295

About this Project

This project will involve the construction of improvements consisting of sanitary sewer, sanitary sewer televising, water mains, storm sewer, retention pond, asphalt streets, curb and gutter, concrete driveway, sidewalks, curb ramps, street signs, pavement striping, pavement markings, street lights, cluster box units, trees, seeding and mulching, and other miscellaneous installations.

Project Schedule

  • Begin Date: August 2017
  • End Date: Spring 2020
  • Project complete: 99%

Project Costs

  • Estimated costs: $3.5 million

Completed Work

  • Sidewalks
  • Diversion rear lot filling
  • Striping
  • Signs
  • Touch up lots next to pond
  • Tree removal
  • Rear lot stabilization
  • Culvert abandonment through levee

Upcoming Work

  • Finish abandonments in Spring 2020