Developer Requested Improvement Projects

The Wilds 20th Addition

  • Completed work: 
    • All underground utilities completed. 
    • Asphalt paving has begun. 
    • Ninth Street W. has been partially paved. 
    • Street light installation is largely complete.
    • Project is substantially complete. 
  • Upcoming work: Issue final completion.

The Wilds 21st Addition

  • Completed work: 
    • Engineering to present engineers report to City Commission for approval to prepare plans and specifications
    • Advertise bids - reading bids July 15
    • Bids have been read. 
  • Upcoming work: 
    • Potentially awarding a contract on the August 2 City Commission meeting.

Westview Third Addition (Phase 2)

  • Project complete.

Westview 4th Addition

  • Project complete. 

Ninth Avenue NE Sanitary Sewer, Water Mains, Fire and Street Improvements

  • Project complete.

The Ranch at The Wilds - Private Project

  • Project complete.